Midcrown and Eisenhauer
PROJECT BACKGROUND AND GOALS
The San Antonio Housing Trust and D2 Councilman McKee Rodriguez are working to transform a vacant 8.6 acres parcel on the City of San Antonio’s Eastside into a community-centered development that integrates affordable senior housing, open space, and a multi-generational community center. The site, located at the intersection of Midcrown Drive and Eisenhauer Road, was acquired in 2024 by the San Antonio Housing Trust (SAHT) with the support of the Inner City TIRZ.
The planning and engagement process led by Borderless Studio from April through October 2025 was guided by two primary objectives:
- to establish a shared community vision for the site, and
- to advance a coordinated, interdepartmental framework for long-term implementation.
FINAL SITE CONCEPT DESIGN
The selected site concept includes 80 units of low-density, affordable senior housing and a ~4 acre park with a multi-generational community center. The project will advance along two coordinated tracks: housing led by the San Antonio Housing Trust and the park and community center by the City of San Antonio.
PLANNING PROCESS and community engagement
The planning effort is rooted in inclusive and community-centered design. The goal was to develop a site plan that reflects shared community values and supports long-term neighborhood well-being. Key phases of the process include:
- Site & Neighborhood Analysis: Understand physical conditions and local context.
- Listening & Learning: Conduct interviews, pop-ups, neighborhood engagements, and surveys with stakeholders and residents.
- Visioning & Strategy Development: Co-develop goals and priorities for the site.
- Concept Design & Feedback: Create preliminary concepts and gather community input through public meetings.
Collaborative Leadership
The planning process, led by SAHT and Borderless Studio, was conducted in close collaboration with key City of San Antonio departments including:
- D2 Council Office
- Planning
- Neighborhood and Housing Services
- Human Services
- Parks and Recreation
- Public Works
- Integrated Community Safety Office
COMMUNITY Engagement activities
Community engagement formed the foundation of the project’s direction. Outreach included bilingual materials, 285 survey responses, two public community meetings, and three pop-up events. In addition, the project team conducted one-on-one conversations while canvassing nearby businesses, engaged with neighborhood groups and associations, coordinated with the Near Northeast Sub-Area Planning process, deployed physical signage, mailed two rounds of postcards to neighbors, and distributed electronic newsletters.
Community Survey
The Community Survey was open from May-June 2025 and was administered throughout surrounding neighborhoods, open to all who live or work in the area. The survey was available in hard copy as well as digitally.
Community Meeting #1: Community Survey Results + Visioning
Midcrown Senior Pavilion. Tuesday, July 15, 6:00-7:30 pm
Community Meeting #2: Site Concepts
PreK4SA East Center. Tuesday, August 26, 6:00-7:30 pm
Community Pop-Ups
- Tuesday, October 7, 6:00-8:00 pm
Roosevelt High School (Neighbors Together Event) - Wednesday, October 15, 6:00 – 7:30 pm
Midcrown Senior Pavilion - Wednesday, October 22, 6:00 – 7:30 pm
Molly Pruitt Library
Site Context & Location
next steps
This Site Concept was approved by the San Antonio Housing Trust Board and the Inner City TIRZ Board in the fall of 2025. In 2026, the property will be subdivided into two parcels to enable parallel delivery and stewardship—housing led by the San Antonio Housing Trust (SAHT), and the park/community center led by the City of San Antonio.
If you want to learn more please reach out to Seema Kairam at the San Antonio Housing Trust.